2024/2025 Annual Business Plan and Budget Public Consultation
Toggle dismiss alert

Council’s Draft Annual Business Plan (ABP) and Budget for the 2024/2025 financial year, which both have regard to the draft Long Term Financial Plan (LTFP), are now available for public consultation.

View more

Dismiss alert
Customer Satisfaction Survey
Toggle dismiss alert

The Light Regional Council has engaged McGregor Tan, Adelaide’s first, home-grown independent market research company, to conduct a customer satisfaction survey.

View more

Dismiss alert

Capital Works

Our rates ensure Council can deliver its capital works to support safe movement throughout our district and improve community amenities. The Capital Works Program provides a complete list of works to be undertaken during the financial year.

Road NameNature of WorkStatus
Research RoadRe-SheetingComplete
Golflinks RoadRe-SheetingComplete
Haydon RoadRe-SheetingComplete
Hazel RoadRe-SheetingNov-Dec
Helson RoadRe-SheetingNov-Dec
Harris RoadRe-SheetingNov-Dec
Fords RoadRe-SheetingOct-Nov
Nitschke RoadRe-SheetingIn Progress
Bagot Well RoadRe-SheetingFeb-Apr
Tremlett RoadConstruct and SealJan-Feb
John Eden RoadConstruct and SealJan-Feb
Gawler River RoadRe-SheetingApr-May
Road NameNature of WorkStatus
Rogers StreetRe-Seal Kerb and Gutter ConstructionDec
Blackwell StreetRe-SealDec
Peake StreetRe-SealDec
Bagot StreetRe-SealNov-Dec
Mattiske StreetRe-Seal Kerb and Gutter ConstructionOct-Nov
Shannahan StreetRe-Seal Kerb and Gutter ConstructionOct-Nov
Stirling StreetRe-Seal Kerb and  Gutter ConstructionNov-Dec
Havelock StreetRe-SealNov-Dec
Rees StreetRe-SealOct-Nov
Road NameNature of WorkStatus
Belvidere RoadConstruction and SealAwaiting Funding Approval
Seppeltsfield RoadConstruction and SealAwaiting Funding Approval
Prescott CrescentRe-SealNov-Dec
Bernard CourtRe-Seal and Kerb ReinstatementNov-Dec
Roseworthy RoadConstruction and SealJan-Feb
Smith RoadRe-SealNov-Dec
Road NameNature of WorkStatus
Peake StreetNew FootpathDec
Rogers StreetNew FootpathDec
Road NameNature of WorkStatus
Berriman RoadFloodway RenewalComplete
Old Anlaby RoadCulvert RenewalIn Progress
Flagstaff Hill RoadFloodway Asset RenewalIn Progress
Stockport Road FloodwayFloodway Surface RenewalOct-Nov
Cliff RoadCulverts Under RoadwayOct-Nov
Schneider RoadFloodway RenewalOct-Nov
ProjectNature of WorkStatus
Wasleys InstituteUpgrade and RepairsIn Progress
Kapunda MuseumUpgrade and RepairsIn Progress
Kapunda InstituteUpgrade and RepairsIn Progress
Bagot's Fortune BuildingUpgrade and RepairsIn Progress
ProjectNature of WorkStatus
Hewett Recreation PrecinctCourt Surfacing and Minor Play Equipment ImprovementsIn Progress
Lions Playground KapundaSenior Play Area RenewalIn Progress
Wasleys Recreation ParkRenewal of Court SurfacingIn Progress
ProjectNature of WorkStatus
CWMS Pump StationsMultiple UpgradesIn Progress
Wastewater Treatment Plant (WWTP)Pump, Aerator and Dewatering Pump UpgradesIn Progress
Reticulation Pipework6 LocationsIn Progress
Recycled WaterFreeling Wetland Pump Station Structure and Fencing RenewalOct-Nov